Transport infrastructure
Study

Prague—Wenceslas Square Stop

Location:
Praha 1 – Nové město
Václavské náměstí
Vodičkova
Investor:
Railway company, state organization
Engineer:
Mott MacDonald CZ, spol. s r.o., AFRY CZ s.r.o., EKOLA group, spol. s r.o., SAGASTA s.r.o., SMA GmbH
Typology:
Transport infrastructure
Status:
Study
Project start:
2025 Q1
Project completion:
N/A
Updated:
3/17/2025
Sources:
spravazeleznic.cz

Diagram of the Prague Railway Junction

Source: Railway Administration

Construction of the Prague—Charles Square Station

Author: Mott MacDonald

Longitudinal section of the station

Author: Mott MacDonald

Transfer Corridor—Můstek B metro station

Author: Mott MacDonald

Exit to the Školská vestibule

Author: Mott MacDonald
01/05

Diagram of the Prague Railway Junction

Source: Railway Administration

A new underground station will be built on Wenceslas Square as part of the Prague Railway Junction. The Railway Administration has presented the future layout of the new tracks in the Prague Railway Junction to the public. Based on a feasibility study, the Central Commission of the Ministry of Transportation selected a variant featuring two separate routes in tunnels and a two-story central station beneath the Central Railway Station.

An increasing number of passengers are using commuter trains in the capital. This must also be taken into account when planning additional rail lines. Therefore, several years ago, the Railway Administration commissioned a feasibility study to address the future design of the Prague Railway Junction.

A central commission of the Ministry of Transport selected the most suitable option, under which two tunnel routes totaling 10.6 kilometers in length and five new stations will be built in the center of Prague. The tunnels will intersect on two levels at the central station beneath the main train station. One will run beneath the existing underpasses to the platforms, while the other will be one level lower. Both parts of the station will be connected by a tunnel with escalators, and the concourses will be located on Winston Churchill Square and in the new departure hall of the Central Railway Station.

Each tunnel will have a capacity of up to 16 trains per hour in each direction. Underground stations will be built in Karlín, on Wenceslas Square, and Chareles Square, as well as a partially underground station at Florenc. The new lines will help separate long-distance and regional transit. This will maintain travel comfort while minimizing the environmental impact. The estimated total cost of this option is CZK 185 billion.

The approved plan will now be incorporated into strategic transportation plans; during its preparation, the Railway Administration will collaborate with state institutions and local governments. Adjustments will also be made to the Principles of Territorial Development and Land Use Plans. The project will provide new rail capacity right in the city center, including several stations that will shorten walking distances for passengers. The result will be not only greater appeal for rail transit but also relief for the busiest public transit routes in the city center. At the same time, the expanded rail network will divert some traffic off the roads. Fewer cars in the city mean lower emissions, less noise, and a significant improvement in the environment.

The feasibility study for the Prague rail hub examined three basic proposals and, additionally, two modifications to one of them. One alternative option included two large stations beneath the Central Railway Station and Wenceslas Square; between them, trains would use a shared four-track section. The second proposed a single central station named Opera. The original design of the selected option was based on faster service with fewer stops.

Construction of the Prague Railway Junction project is planned for the years 2035–2047.